Update june 2016 we now have frames





Land registered - 3rd feb 2016
Construction list - 22nd april
Site peg out - 18th april 
Peiring - 10th may 
Slab - 22nd may 
Frames - 13th -15th june

Tuesday 7 July 2015

Update July 2015

Still waiting on land currently being developed.
We won a facebook competition on the estates facebook and got to go onsite for a tour 

We got to see our block pegged out for size 
At this stage the current timeline from developer is start of October finish development and November / December registration

My personal prediction would be more like feb/march registration 2016. Fingers crossed 

Monday 25 August 2014

Colour selections!!



On Friday we had our colour appointment at oak flats
We had lee she was really helpful :)
We also had our plan presentation with our CLO 

$$$ indicates upgrade 

This is the facade we have chosen Balinese tropicana


This is our inspiration for colours eventually we would like to render the main front pole in a darker brown colour 

Externals


Brick- Austral everyday engage
Roof/gutters - Jasper
Facia / windows- Surfmist
Cladding - Taubmans Coffee cake
Garage door / water tank - Jasper




Bathrooms/ensuite



Ensuite - Semi frameless shower $$$
Bathroom - Silver shower $$$
Stone bench top- Ceaserstone nimbus 
Cupboards-Polytec Createc Malt gloss $$$
Set of drawers -$$$
Tile- Waterford Marfil Matt 300x300 to floor
Waterford Marfil gloss to walls
Toilet/towel rail - Standard
Shower nook to ensuite $$$
Showerhead - Caroma Quatro $$$ 




Kitchen 


Flooring - Gerflor clic creation vinyl planks in colour wild oak $8900 

Bench top - 40mm plus waterfall edges in White shimmer $$$
Kitchen cupboards - Polytec Createc strata grey gloss $$$
Bar back -Polytec Createc stone Greg gloss $$$
Splash back - White tile 3 dimensional 300x600 
Soft close to all- $$$
Pot drawers- $$$

Inbuilt study desk -  Tessuto Milan Matt 
Internal wall colour - Taubmans Ageless



Front door lock
Trilock omni allure lever $$$ 



All internal doors except spare bedrooms 

Lin 1 with Gainsborough Linear pull handle as shown in photo 

Saturday 26 July 2014

The house ..

Building Mcdonald Jones Homes Havana one
Major changes
-Extra meter width in garage
-Flipped front of house to suit block
-Extra 470mm length to Ensuite walk in robe and entrance foyer

These are pictures of the Show home at brooks reach but we are doing most of the house the exact same

                                                             Main entrance hallway
 
 
Main bedroom


 Ensuite - Identical except for frameless shower instead
 
The theatre room- This photo does it no justice!
 
 
                                           
                                                                      Living dining
Also getting this flooring aswell Gerflor Wild Oak
 
 
                                                  
Amazing kitchen :)  Everything the same in here cupboards polytec strata grey
                     

                                               
All Internal doors (Lin 1 )Doors same
Double doors here go through to "Childrens activity area" and bedrooms

 
 
 
Childrens activity area




 Main bathroom only cupboard colour will be slightly different




Outdoor alfresco of course we will only have a concrete slab but will  work on the timber decking after we settle in

The Land..

Lynden Views Kembla Grange is located on West Dapto road. There will be quite a few stages on this land which im sure will take quite a few years to register and build on. We will be in stage 1
There is a neighborhood plan in place that has a sporting ground and small shopping Centre and I think I may have read something about a school at one stage? hope so!

We are Still currently waiting for the DA to be approved by council but at this stage site cut is set for Mid- August if this goes to plan who knows. We are already behind as when we signed with our builder on May 25th 2014 we were told site cut would be in June 2014. Things at this stage aren't looking like they will run on time and I already feel as if it will be a long wait till land is registered.
There is not much info that can be found just yet on the estate online only really the house and land packages. Hopefully they get into it soon.

The photos show the hill with the trees ( Looking up at where stage 1 will be) our block I imagine in my head anyway will be just to the right of the furthermost right tree almost at the peak of the hill. It is hard to imagine as were only going off plans at this stage .

The other photos show the view